Konza Technopolis investment, infrastructure and usage indicators, 2020 to 2025
Sources checked
- 2020The project recorded 5 km of road infrastructure, one completed building and three data centre clients.
- 2021The reported road network reached 15 km. The data centre hosted 14 clients.
- 2022Road infrastructure reached 25 km. The data centre hosted 41 clients and cumulative investment reached KSh 59.25 billion.
- 2023Reported fibre reached 50 km and road infrastructure 35 km. The Integrated Operations Centre was at 35% completion.
- 2024Road infrastructure reached 45 km and fibre 79 km. The Integrated Operations Centre was at 82% completion.
- 2025Road and fibre lengths held steady. The Integrated Operations Centre reached 100% reported completion and the data centre hosted 171 clients.
Select a year to inspect reported infrastructure and operational milestones.
Konza Technopolis investment, infrastructure and usage indicators, 2020 to 2025
The KNBS workbook identifies the Konza Technopolis Development Authority as the source. The 2025 survey figures are provisional. The table omits observations the source leaves blank or marks with a dash. Road length and investment stock are cumulative measures.
| Source | ||||
|---|---|---|---|---|
| 2020 | Cumulative investment | KSh billion | 27.05 | Source 1 |
| 2020 | Annual investment | KSh billion | 11.53 | Source 1 |
| 2020 | Investors | count | 14 | Source 1 |
| 2020 | Total revenue | KSh million | 40.25 | Source 1 |
| 2020 | Data centre clients | count | 3 | Source 1 |
| 2020 | Cloud storage used | % | 25 | Source 1 |
| 2020 | Road infrastructure length | km | 5 | Source 1 |
| 2020 | Road construction in year | km | 5 | Source 1 |
| 2020 | Power utilization | MW | 2 | Source 1 |
| 2020 | Completed buildings | count | 1 | Source 1 |
| 2020 | Buildings under construction | count | 8 | Source 1 |
| 2020 | Conference facility completion | % | 5 | Source 1 |
| 2020 | KAIST completion | % | 5 | Source 1 |
| 2021 | Cumulative investment | KSh billion | 43.85 | Source 1 |
| 2021 | Annual investment | KSh billion | 16.8 | Source 1 |
| 2021 | Investors | count | 30 | Source 1 |
| 2021 | Total revenue | KSh million | 64.34 | Source 1 |
| 2021 | Cloud revenue | KSh million | 1.4 | Source 1 |
| 2021 | Data centre clients | count | 14 | Source 1 |
| 2021 | Cloud storage used | % | 43 | Source 1 |
| 2021 | Road infrastructure length | km | 15 | Source 1 |
| 2021 | Road construction in year | km | 10 | Source 1 |
| 2021 | Power utilization | MW | 2 | Source 1 |
| 2021 | Completed buildings | count | 2 | Source 1 |
| 2021 | Buildings under construction | count | 7 | Source 1 |
| 2021 | Conference facility completion | % | 20 | Source 1 |
| 2021 | KAIST completion | % | 31 | Source 1 |
| 2022 | Cumulative investment | KSh billion | 59.25 | Source 1 |
| 2022 | Annual investment | KSh billion | 15.4 | Source 1 |
| 2022 | Investors | count | 52 | Source 1 |
| 2022 | Total revenue | KSh million | 307.39 | Source 1 |
| 2022 | Cloud revenue | KSh million | 27.35 | Source 1 |
| 2022 | Data centre clients | count | 41 | Source 1 |
| 2022 | Cloud storage used | % | 60 | Source 1 |
| 2022 | Road infrastructure length | km | 25 | Source 1 |
| 2022 | Road construction in year | km | 10 | Source 1 |
| 2022 | Walkway length | km | 10 | Source 1 |
| 2022 | Power utilization | MW | 3 | Source 1 |
| 2022 | Completed buildings | count | 2 | Source 1 |
| 2022 | Buildings under construction | count | 9 | Source 1 |
| 2022 | Conference facility completion | % | 55 | Source 1 |
| 2022 | KAIST completion | % | 42 | Source 1 |
| 2023 | Cumulative investment | KSh billion | 69.89 | Source 1 |
| 2023 | Annual investment | KSh billion | 10.64 | Source 1 |
| 2023 | Investors | count | 56 | Source 1 |
| 2023 | Total revenue | KSh million | 191.3 | Source 1 |
| 2023 | Cloud revenue | KSh million | 35.57 | Source 1 |
| 2023 | Data centre clients | count | 87 | Source 1 |
| 2023 | Cloud storage used | % | 78 | Source 1 |
| 2023 | Fibre installed | km | 50 | Source 1 |
| 2023 | Integrated Operations Centre completion | % | 35 | Source 1 |
| 2023 | Smart poles | count | 60 | Source 1 |
| 2023 | Signalled junctions | count | 6 | Source 1 |
| 2023 | Road infrastructure length | km | 35 | Source 1 |
| 2023 | Road construction in year | km | 10 | Source 1 |
| 2023 | Walkway length | km | 25 | Source 1 |
| 2023 | Power utilization | MW | 4 | Source 1 |
| 2023 | Water reclamation facility utilization | m³ per day | 1,800 | Source 1 |
| 2023 | Water treatment plant utilization | m³ per day | 3,100 | Source 1 |
| 2023 | Completed buildings | count | 7 | Source 1 |
| 2023 | Buildings under construction | count | 12 | Source 1 |
| 2023 | Conference facility completion | % | 72 | Source 1 |
| 2023 | KAIST completion | % | 69 | Source 1 |
| 2023 | Riara University phase one completion | % | 17 | Source 1 |
| 2024 | Cumulative investment | KSh billion | 83.48 | Source 1 |
| 2024 | Annual investment | KSh billion | 13.59 | Source 1 |
| 2024 | Investors | count | 70 | Source 1 |
| 2024 | Total revenue | KSh million | 252.36 | Source 1 |
| 2024 | Cloud revenue | KSh million | 151.6 | Source 1 |
| 2024 | Data centre clients | count | 134 | Source 1 |
| 2024 | Cloud storage used | % | 75 | Source 1 |
| 2024 | Fibre installed | km | 79 | Source 1 |
| 2024 | Integrated Operations Centre completion | % | 82 | Source 1 |
| 2024 | Smart poles | count | 81 | Source 1 |
| 2024 | Signalled junctions | count | 12 | Source 1 |
| 2024 | Road infrastructure length | km | 45 | Source 1 |
| 2024 | Road construction in year | km | 10 | Source 1 |
| 2024 | Walkway length | km | 45 | Source 1 |
| 2024 | Power utilization | MW | 5 | Source 1 |
| 2024 | Water reclamation facility utilization | m³ per day | 3,600 | Source 1 |
| 2024 | Water treatment plant utilization | m³ per day | 6,200 | Source 1 |
| 2024 | Completed buildings | count | 9 | Source 1 |
| 2024 | Buildings under construction | count | 11 | Source 1 |
| 2024 | Conference facility completion | % | 75.67 | Source 1 |
| 2024 | KAIST completion | % | 93 | Source 1 |
| 2024 | Riara University phase one completion | % | 89 | Source 1 |
| 2025 | Cumulative investment | KSh billion | 99.38 | Source 1 |
| 2025 | Annual investment | KSh billion | 15.9 | Source 1 |
| 2025 | Investors | count | 78 | Source 1 |
| 2025 | Total revenue | KSh million | 202.9 | Source 1 |
| 2025 | Cloud revenue | KSh million | 126.7 | Source 1 |
| 2025 | Data centre clients | count | 171 | Source 1 |
| 2025 | Cloud storage used | % | 50 | Source 1 |
| 2025 | Fibre installed | km | 79 | Source 1 |
| 2025 | Integrated Operations Centre completion | % | 100 | Source 1 |
| 2025 | Smart poles | count | 141 | Source 1 |
| 2025 | Signalled junctions | count | 12 | Source 1 |
| 2025 | Road infrastructure length | km | 45 | Source 1 |
| 2025 | Road construction in year | km | 0 | Source 1 |
| 2025 | Walkway length | km | 45 | Source 1 |
| 2025 | Power utilization | MW | 6 | Source 1 |
| 2025 | Water reclamation facility utilization | m³ per day | 6,000 | Source 1 |
| 2025 | Water treatment plant utilization | m³ per day | 10,000 | Source 1 |
| 2025 | Completed buildings | count | 17 | Source 1 |
| 2025 | Buildings under construction | count | 26 | Source 1 |
| 2025 | Conference facility completion | % | 78 | Source 1 |
| 2025 | KAIST completion | % | 100 | Source 1 |
| 2025 | Riara University phase one completion | % | 97 | Source 1 |