Konza Technopolis grew its data centre and building stock as road length held steady

Konza reported 171 data centre clients and 17 completed buildings in 2025, up from 134 and nine a year earlier. Reported road and fibre lengths were unchanged. The project records separate building work, utility use, digital services and investment.

Sources checked

2020 to 2025Six years of physical and digital development at Konza
  1. 2020
    The project recorded 5 km of road infrastructure, one completed building and three data centre clients.

    Source 1

  2. 2021
    The reported road network reached 15 km. The data centre hosted 14 clients.

    Source 1

  3. 2022
    Road infrastructure reached 25 km. The data centre hosted 41 clients and cumulative investment reached KSh 59.25 billion.

    Source 1

  4. 2023
    Reported fibre reached 50 km and road infrastructure 35 km. The Integrated Operations Centre was at 35% completion.

    Source 1

  5. 2024
    Road infrastructure reached 45 km and fibre 79 km. The Integrated Operations Centre was at 82% completion.

    Source 1

  6. 2025
    Road and fibre lengths held steady. The Integrated Operations Centre reached 100% reported completion and the data centre hosted 171 clients.

    Source 1

Select a year to inspect reported infrastructure and operational milestones.

Source 1 Source 2 Source 3

The data centre hosted more clients while recorded cloud revenue fell

The data centre hosted 134 clients in 2024 and 171 in 2025, a gain of 37. Reported cloud revenue fell from KSh 151.60 million to KSh 126.70 million. Used cloud storage fell from 75% to 50% of available resources. Client counts, reported revenue and capacity use can move in different directions. Source 1 Source 2

Road length held while the smart city control system advanced

The project reported 45 km of road infrastructure and 79 km of fibre in both 2024 and 2025. It recorded 141 smart poles in 2025, up from 81, while the Integrated Operations Centre’s reported completion rose from 82% to 100%. The authority describes that centre as a central point for functions including traffic control and environmental monitoring. Source 1 Source 2 Source 3

Reported use increased for power and water services

Power utilization reached 6 MW in 2025 compared with 5 MW in 2024. The water reclamation facility’s recorded utilization rose from 3,600 to 6,000 cubic metres per day, and the water treatment plant from 6,200 to 10,000. These are usage measures, distinct from rated plant capacity. Source 1 Source 2

Building activity and investment describe separate milestones

The table shows 17 completed buildings and 26 under construction in 2025. It records 78% completion for the conference facility, 97% for the first phase of Riara University and 100% for Kenya-AIST. Cumulative investment reached KSh 99.38 billion, with KSh 15.90 billion invested during the year. Compare the annual flow with the cumulative project figure. Source 1 Source 2